We handle residential renovations in GTA homes for owners who want one contractor responsible for the whole job. That might be a complete home renovation, an addition, an in-law suite or garden suite, or several rooms done together before you move into a house you just bought. Home Best Solutions holds a Building Renovator licence with the City of Toronto and works across Toronto, including North York and Scarborough, and in York Region. We pull the permit, bring in the engineer and designers when the work calls for them, and book every licensed trade in the right order. The person who quotes your project is the person you call while it’s being built.
We’ll walk the house with you and point out which parts need a permit.
Our residential renovation services cover whole houses, new living space, single rooms, structural and finishing work, and decks. Most clients book two or three of those at once, and we run the site and every trade on them. A few things sit with specialists:
A complete home renovation is the project we’re set up for. It usually means opening up the main floor, a new kitchen, one or more bathrooms, new floors and stairs, and often the basement, under one contract. Many clients book it between closing and moving in, while the rooms are empty. With one schedule for every room, the drywall crew isn’t waiting on a plumber someone else booked, and the flooring goes in once, after the dusty work is done. We walk the house before quoting so the price reflects what we can see behind the walls.
Home additions add the space your lot allows, but the house doesn’t have yet: a rear addition for a bigger kitchen and family room, a second story over a bungalow, or a ground-floor bedroom for a parent who can’t manage stairs. Each one needs zoning review, a building permit, drawings from our partner architect or designer, and structural engineering. We coordinate those, then handle excavation, footings through licensed foundation trades, framing, and roofing. The hard part is joining new to old so the floors line up and the heating reaches the new rooms. Most additions also mean renovating the rooms they connect to, and having one contractor for both saves weeks of back-and-forth.
An in-law suite renovation turns part of the house, usually the basement, into a self-contained unit for a parent or an adult child. A suite has its own kitchen, bathroom, and sleeping area. To be legal, it needs a building permit and must meet the Ontario Building Code and your municipality’s rules for additional residential units, which in practice means fire separation between the units and a safe exit that doesn’t pass through the other unit. For aging parents, we build the bathroom barrier-free, with a curbless shower and grab-bar blocking, following CSA B651 guidance. If the suite is for a family member aged 65 or older, or an adult relative who qualifies for the disability tax credit, ask your accountant about the federal Multigenerational Home Renovation Tax Credit before work starts.
Garden suites are small detached homes in the rear yard, and each GTA municipality sets its own rules. In Toronto, they’re permitted in most residential zones under Chapter 150.7 of Zoning By-law 569-2013, and a suite that meets the by-law can go straight to a building permit. Fire access from the street and existing trees often decide where the suite can sit. We start with a zoning check, bring in partner designers for the drawings, and plan servicing early, because running water, sewer, power, and heat to the back of the lot is often the biggest budget unknown.
If you own a lot and want to build a new home, our custom home building service covers construction, with architectural drawings from partner architects. Ontario generally requires anyone building a new home under contract on the owner’s land to hold a Home Construction Regulatory Authority (HCRA) licence and enrol the home with Tarion before construction starts. Whoever you hire, check the HCRA’s Ontario Builder Directory before you sign.
If an addition, a suite or a whole-house renovation is on your list, we’ll explain the permit route for your lot on the first visit.
Call us to book that visit:
Most kitchen renovations we take on involve more than new cabinets. When the kitchen is closed off from the dining room, the job can include removing a wall, moving the sink or range, new circuits from our Licensed Electrical Contractor, and a gas line from a licensed gas fitter. Rough-ins and inspections come before drywall, and cabinets and counters go in after the floors. For bigger projects, we schedule the kitchen early so you get it back sooner.
Our bathroom renovations cover powder rooms, family bathrooms, and ensuites, often two or three in the same house. Schluter is our standard waterproofing system, and we flood-test every waterproofed shower pan before tile goes down, because a leak found after tiling means tearing the shower out. For clients who need step-free access, we build curbless showers with a recessed, sloped floor, following CSA B651 guidance. Plumbing moves are worked out at design, so the layout you approve is one the house can take.
A basement renovation usually adds a family room, a guest bedroom with a bathroom, an office, or the first stage of a legal suite. We check for moisture before framing, insulate the foundation walls, and plan headroom around ducts and beams, since the Building Code sets minimum ceiling heights for living space. If you might want an in-law suite later, tell us now. Fire separation and egress cost far less to build in at the start than to add after drywall.
A condo renovation runs on the building’s rules as much as ours. We get board or property manager approval where the declaration requires it, book the service elevator, work within the building’s hours, and protect the hallways. Concrete slabs limit where drains can move, and some buildings set rules for the underlay that goes under hard flooring, so we confirm those details with management before you choose finishes. Most condo owners ask us to do the kitchen and bathroom together, sometimes with new flooring throughout the suite.
Opening up the main floor is part of most of our complete renovations. For load-bearing wall removal, an engineer designs the beam, posts, and support down to the footing, and a building permit is required. We coordinate both, shore the floor above, install the beam to the engineer’s drawings, and patch floors and ceilings.
Textured ceiling finishes in older homes can contain asbestos, which was used widely in Canadian homes before 1990, so before popcorn ceiling removal, the ceiling is tested. If the result is positive, a qualified abatement contractor removes it first. Then we skim-coat, prime, and paint the ceiling smooth, usually before new floors go in so the dust never touches them.
Our interior painting and drywall work covers new walls after layout changes, repairs where trades opened walls, patching older plaster, and painting through the house. On bigger jobs, we paint before the new floors go down and touch up after trim, so drips and ladder marks never land on finished flooring.
With floor removal and installation, we lift old carpet, tile, or hardwood, level the subfloor, and lay hardwood, engineered wood, vinyl plank, laminate, or tile. Once walls come out, most clients want one floor running through the main level, and where possible we weave new boards into existing hardwood.
Worn or carpeted stairs stand out once the surrounding floors are new. Our stair renovation and refinishing work includes new treads and risers, refinishing existing oak, and new pickets and railings in wood, metal, or glass. We stain or finish the stairs to match the new flooring so the two read as one.
Custom cabinetry and millwork covers built-ins, wall units, closets, vanities, mudroom benches, and trim. We measure on site after drywall, coordinate fabrication, and install to finished floors and walls, using materials such as painted MDF or wood veneer to suit the budget.
Our deck and outdoor living work includes ground-level and raised decks, stairs, railings, and decks over living space or on rooftops. Footings are helical piles or hand-dug sonotubes, depending on soil and access. A deck over living space gets a waterproof membrane and drainage layer before the decking goes on. We offer pressure-treated, cedar, composite, and PVC decking with aluminum, glass, or wood railings, chosen for your budget and how much upkeep you want. In Toronto, a deck more than 60 cm (24 inches) above the ground needs a building permit, and other municipalities set their own rules, so we confirm what applies before quoting.
Hire separate trades for each room, and you become the scheduler. On our projects, one plan covers the house, usually in this order:
On a full house renovation of a Toronto bungalow in 2021, we found asbestos before starting, so a licensed removal company took it out and issued clearance first. The job then included removing a load-bearing wall with an engineer’s drawings and a permit, a new kitchen, hardwood floors, popcorn ceiling removal, a bathroom, and the basement. In Richmond Hill, returning clients had us do a whole-townhouse renovation in 2026, with two bathrooms, a rebuilt staircase and railing, a new kitchen and a basement bathroom. More are in our project gallery.
Send us your list of rooms and we’ll turn it into one plan and one quote.
Call us or send the list through the quote form:
Toronto Building issues permits for all of Toronto, including North York and Scarborough, and every building permit application there to construct or demolish needs a Tree Declaration Form. In York Region, each municipality runs its own office: Building Standards in Vaughan and in Markham, the Building Division in Richmond Hill, and Building Services in Newmarket. Drawings, fees, and inspection booking differ, so we prepare each submission to that city’s requirements.
In a house built before 1990, like the Toronto bungalow described above, we plan for asbestos testing on textured ceilings, and for wiring or electrical service that may need upgrading. The oldest houses can also have plaster walls. A newer subdivision home usually hides less, so more of the budget goes to layout and finishes.
Frozen ground slows excavation and footings, so we aim to close in additions, garden suites, and custom homes before winter and keep interior work for the cold months.
Call us and we’ll check the zoning for your address before you pay for drawings.
Most clients stay home during room renovations. We keep one bathroom in use while another is rebuilt, and when the kitchen is replaced, we can set up a temporary sink and counter elsewhere in the house. Work areas are sealed with plastic barriers and zipper doors, floors and stairs are covered, and the site is cleaned at the end of each day.
A complete home renovation is different. When the kitchen, bathrooms, and floors are all torn out at once, or the job involves structural work or asbestos abatement, moving out for part or all of it is usually faster and safer for your family. We’ll tell you which applies when we quote. Timelines depend on size and the permit route, and our schedule includes permit review.
Home Best Solutions was founded in 2017. Our owner, Reza Milani, has more than 20 years of hands-on renovation experience. We’ve completed more than 200 projects and run several jobs at a time with a full team of trades, but you still deal directly with the owner, and the person who quotes your renovation stands behind it.
We quote after a site visit, by room and by trade, so you can see what each part costs and add or remove items. These move the number most:
We’ll send a quote broken out by room.
For residential renovation in GTA homes, call Home Best Solutions at (647) 862-6050. We’ll walk the house with you and send one quote for the whole project, or you can send your details through our contact form, and we’ll call you back.
Ready to plan your residential renovation?
Call us, or request a site visit through the quote form:
Yes. As your residential contractor, we coordinate the designers and engineers who prepare drawings, submit the permit, schedule licensed trades, and book inspections. You sign one contract and deal with one owner.
In most GTA municipalities, it can, if the house meets the zoning rules and Ontario Building Code requirements for an additional residential unit. Unit limits, parking, and registration rules differ by municipality, so we check your address before planning the suite.
We build garden suites where zoning allows, with partner drawings and a building permit. For new custom homes, Ontario’s HCRA licensing and Tarion enrolment rules apply, and we confirm the licensing and warranty arrangements for your project before any contract is signed.
We hold a Building Renovator licence with the City of Toronto, no. T854882717, and carry WSIB coverage and liability insurance. Licensed trades handle electrical, gas, and structural work, and you can ask to see the certificates when we visit.
That depends on the job size and whether it needs a permit. You get a written schedule with the quote, including time for permit review.